Balochistan Energy Department Solar Hybrid System Tender Corrigendum
Tender advertisement published in Jang on Saturday, 31 October 2026, listed under Quetta.
The original image is temporarily unavailable. Use the source link or the details below. Open the full-size clipping Advertisement details
The Chairman Procurement Committee, Office of the Director General (North), Energy Department, has issued a corrigendum amending the bidding documents for solar hybrid system works under TSE No. 2627101203263.
Corrigendum reference No. DG(N)/ED/2026/1023-B relates to PRQ No. 1742/06-10-2026, published on October 7, 2026. The amended requirements are:
| Requirement | Amended Condition |
|---|---|
| Completed project experience | The firm must have successfully completed one similar project involving installation of a solar hybrid system in the government sector during the last five years, worth at least 40% of the total project cost. This condition is marked as an alternative. |
| PEC registration | Registration with the Pakistan Engineering Council (PEC) in category C-4 or above, up to 200 million, in the relevant category with specialized code EE05 (High Voltage). This condition is marked as an alternative. |
| Similar completed works | The firm must have successfully completed similar solar hybrid system installation works in the government sector during the last five years, each worth at least 30% of the total project cost. |
| Similar works in hand | The firm must have similar solar hybrid system installation works in hand in the government sector during the last five years, each worth no less than 30% of the total project cost. |
Bidders are requested to download the amended bidding documents. All other terms and conditions remain unchanged.
Issued by the Chairman Procurement Committee, Office of the Director General (North), Energy Department. Publication reference: PRQ No. 2172/30-10-2026. Website: www.dpr.gob.pk.
Published in Jang on Saturday, 31 October 2026. DailyAds.pk indexes newspaper advertisements; the original notice and the issuing organisation remain the source for final terms and eligibility.